Labour Calls For Transpennine Express Rail Contract Removal

Labour is calling for train operator Transpennine Express to have its contract removed.

Transpennine, which operates across the North of England and into Scotland, has been cancelling trains on a daily basis for months.

Labour's shadow transport secretary Louise Haigh said the service had "never been worse".

Rail Minister Huw Merriman said that if the service "can't be turned round then decisions will be made".

When rail franchises fail in England, they are taken over by a Department for Transport-owned company called the Operator of Last Resort (OLR).

Ms Haigh asked in the House of Commons on Thursday for this to happen to Transpennine.

The train company's contract is up for renewal in May.

Mr Merriman responded that he was "keen to ensure the [OLR] has a manageable portfolio" but "decisions will be made" on Transpennine if it cannot turn itself around.

However, he added that there had been criticism about the performance of another rail operator, Northern, which is currently run by the OLR.

London and North Eastern Railway (LNER) and Southeastern Trains are also run by the OLR.

Cancellations

Transpennine has blamed its cancellations on high sickness rates and a backlog of driver training caused by the pandemic.

However on Thursday the Office of Rail and Road (ORR), told the rail industry it must be more transparent about late changes to services.

The rail industry uses a process known as "p-coding" to make advance cancellations, when not enough staff or trains are available.

"P-coding" means trains are taken out of the schedules before 10pm the night before and don't count as on-the-daycancellations - even though passengers wake up to find their train has disappeared from timetables.

The ORR said historically this had been used so emergency timetables could be introduced because of poor weather or damage to infrastructure. Performance is measured against those emergency schedules.

The regulator said an investigation had found a gap between cancellation statistics and what passengers experienced.

The Rail Minister Huw Merriman this week expressed concern at how much Transpennine Express has been using "p-coding", and said he would meet the ORR to discuss the practice.

Rest day working

The train operator also lacks a current agreement on rest day working with the drivers' union Aslef.

On Wednesday, Mick Whelan, Aslef's general secretary, was asked on the BBC's Today programme why members had not been given a vote on an offer of 1.5 times pay for working overtime.

He responded that pay had not gone up in several years, and the point of rest day working was not to cover services.

Asked if an agreement on rest day working would mean more trains running, he said: "I don't think my people would work those trains for a lower rate of pay even if we had an agreement."

Mr Whelan added: "We have a company that's operating in totally bad faith and smashing every agreement we've got".

He said Transpennine has "poor performance, poor industrial relations and can't operate in the 21st Century".

Ministers have repeatedly said a reliance on rest day working needs to end.

Flat out

A Transpennine Express spokesperson said the company was "committed to the communities we serve and want to assure our customers that we are doing all we can to deliver a train service they can rely on".

The firm had removed services from its timetable on a day-to-day basis due to "very high levels of sickness and a training backlog following the pandemic", said the spokesperson, adding that Transpennine "continues to work flat-out to deliver higher levels of service delivery and to tackle the issues that are being experienced by customers".

Image source, Getty Images

Image caption,

Louise Haigh called for the Transpennine contract to be removed

Mr Merriman had already said on Wednesday that Transpennine Express' contract was under consideration.

He told the Transport Select Committee: "If a train operator is not performing and it appears clear that they can't perform and can't turn this around, then that contract would come to an end and we wouldn't hesitate to put it into the Operator of Last Resort."

"I am already looking at what needs to be done... with regards to that contract," he added.

Mr Merriman said he had weekly data on Transpennine and another troubled operator, Avanti West Coast, and what they were doing to improve performance.

Avanti

The government recently gave another troubled operator, Avanti West Coast, six months to urgently improve.

Mr Merriman has said Avanti had increased services in December without relying on rest day working, and recruited more drivers, but a period of industrial action over Christmas meant it was hard to assess whether improvements were working.

He said Avanti's performance had been much improved over the past couple of weeks and he hoped the operator was "turning a corner".

RECENT NEWS

Metas Yann LeCun: Current AI Methods Wont Achieve Human-Level Intelligence

Yann LeCun, Meta’s chief AI scientist, has made a bold assertion that large language models (LLMs) will not achieve hu... Read more

XAI Nears $6 Billion Funding Round With New Investments From Leading VCs

Elon Musk’s artificial intelligence venture, xAI, is on the verge of completing a significant $6 billion funding round... Read more

Legal Challenges In Sachin Dev Duggals Entrepreneurial Journey

Sachin Dev Duggal, the visionary founder of Builder.ai, has achieved remarkable success in the tech industry. However, h... Read more

Vertex Ventures To Raise $65 Million For Japan-Focused Fund

Singapore – Vertex Ventures, the venture capital subsidiary of Temasek, is set to launch its first fund dedicated to J... Read more

Tech Industry Takes On Nvidias CUDA With Open-Source AI Software Solutions

Seattle, WA — In a bid to diversify the AI development ecosystem, OpenAI and a coalition of tech companies are working... Read more

Huawei's 'AI-in-a-Box' Solutions Threaten Cloud Market Leaders

Shanghai, China — Huawei is at the forefront of a new trend in the tech industry: 'AI-in-a-box' products that empower ... Read more